Works on Northcote Street

Starting on September 11, 2017 
A temporary water system will be installed
Pulverization of the existing asphalt


Starting on September 13, 2017
Excavation to replace the drinking water and sewer lines


From October 13 to November 3, 2017

Construction of curbs, paving and surface repairs